Re-measurement of the total length changed the adjusting value from 10cm into 12cm thinking over the convenience for setting and AC wiring actually.
This kind of precise adjustment would be effective after finishing the work.

X-Ray room has been covered with thin 1,5mm thickness lead plate thoroughly, this kind of plating procedure is indispensable for the delivering some specific form to the Public Agency, this is an obligation in accordance with the Law of Radiation Hazards Prevention.

About 80% of inner room designing has been embodied these days but with wooden surface. I'm looking forward to see finished one on 14th next month, possible?
The sign designing plate outside is not yet, just drawing only, let them make haste!

As for working chair, unnecessary device like air filter & water filter bracket was removed and water supplying hoses must be replaced otherwise peeing of water would trigger board printed electric circuitry shortening leading to solenoid coil thermal fuse breaking that had been brought before.